Activities in August and September 2010
Bond Closing - August 12, 2010
Notice to Proceed - August 18, 2010
Construction Mobilization - August 23, 2010
GA Power Utility Relocations -Complete
Building Pad - Complete
Building Foundations - Ongoing
Cistern Concrete - Complete
West Entrance Drive Relocation - Complete
Anticipated Construction Milestones
Steel Structure Start - October 25, 2010
Pool Shells Complete - December 2010
Structural Steel Complete - January 2011
Building Enclosed - April 2011
Material Completion/Occupancy - October 2011